Milestones

  • April 2016
    Plant EPC Contract with GE/Daewoo E&C - Initialed

  • April 2016
    Plant site's Land Title (Certificate of Occupancy) – Granted by the Anambra State Government

  • February 2016
    TLA signed by CPG & TCN

  • January 2016
    Plant ESIA, published on the World Bank's website. Click here for details

  • June 2015
    Power Purchase Agreement (PPA) - initialed

  • June 2015
    Transmission and sub-station EPC bidders selection – (completed)

  • December 2014
    EPC & LTSA Contractor Selection

  • August 2014
    Signed on FCMB Capital Markets Limited as the MLA for the BOI-PAIF and the Local debt tranche

  • April 4th 2014
    Century Power to raise $700 Million for Gas-Power Plant. Read more at Bloomberg.com

  • July 29th 2013
    CPG releases EPC Request for Pre-Qualification Document for Okija switchyard, Onitsha 330KV substation and Nnewi 330KV/132KV substation. Click here to download.

  • July 29th 2013
    CPG releases EPC Request for Pre-Qualification Document for Nnewi-Okija-Onitsha 330KV transmission line. Click here to download.

  • May 3rd 2013
    New Bid Clarification released. Click here to download.

  • April 23rd 2013
    CPG-Okija IPP Bid Clarification released. To download, click here.

  • April 8th 2013
    CPG releases EPC tender documents for Okija IPP.

    The tender documents are now available here.

  • March 2013
    CPG completes site clearing on Okija site.

  • February 2013
    CPG obtains permission from TCN to connect to the grid at the Onitsha substation.

  • November 27 2012
    CPG obtains clearance from Federal Ministry of Environment to build Okija IPP.

  • September 2012
    Signed on AfDB as the lead financial arranger for the project.

  • August 2012
    CPG’s ESIA approved by the Federal Ministry of Environment.

  • July 2012
    Century Power hires AF-Consult as owner's engineer for Okija IPP.